Sizing Condensate Return Lines

A guide to sizing condensate lines to and from steam traps, including examples and calculations using the condensate pipe sizing chart.

Sizing Condensate Return Lines

Sizing Condensate Return Lines

The four main types of condensate line, as mentioned in Module 14.2, are shown in Table 14.3.1:

Table 14.3.1 The four basic types of condensate line

Type of condensate lineCondensate line is sized to carry the following
Drain lines to trapCondensate
Discharge lines from trapsFlash steam
Common return linesFlash steam
Pumped return linesCondensate

Sizing of all condensate lines is a function of:

  • Pressure - The difference in pressure between one end of the pipe and the other. This pressure difference may either promote flow, or cause some of the condensate to flash to steam.
  • Quantity - The amount of condensate to be handled.
  • Condition - Is the condensate predominately liquid or flash steam? With the exception of pumped return lines which will be discussed in Module 14.4, the other three main types of condensate line and their sizing, will be covered in this Module.

Sizing drain lines to traps

Sizing drain lines to traps

It should not be assumed that the drain line (and trap) should be the same size as the plant outlet connection. The plant may operate at a number of different operating pressures and flowrates, especially when it is temperature controlled. However, once the trap has been correctly sized, it is usually the case that the drain line will be the same size as the trap inlet connection, (see Figure 14.3.1).

Learn about steam

Regarding the conditions inside the drain line, as there is no significant pressure drop between the plant and the trap, no flash steam is present in the pipe, and it can be sized to carry condensate only.

When sizing the drain line, the following will need consideration:

  • The condensing rate of the equipment being drained during full-load.
  • The condensing rate of the equipment at start-up. At plant start-up, the condensing rate can be up to three times the running load – this is where the temperature difference between the steam and colder product is at its maximum. The drain line, trap, and discharge line also have to carry the air that is displaced by the incoming steam during this time. The sizing routine for the steam trap will have to consider both of these variables, however, in general:
  • For steam mains drainage, the condensate load for each drain trap is typically 1% of the steam capacity of the main based on drain points at 50 m intervals, and with good insulation. For most drain points, sizing the trap to pass twice the running load at the working pressure (minus any backpressure) will allow it to cope with the start-up load.
  • On constant steam pressure processes such as presses, ironers, unit heaters, radiant panels and boiling pans, sizing the traps on approximately twice the running load at the working pressure (less any backpressure) will provide sufficient capacity to cope with the start-up load.
  • On temperature controlled applications, the steam pressure, the plant turndown, the set temperature and steam trap location need to be considered in detail, and the trap needs to be sized to cater for both the full and minimum load conditions. If these conditions are not known it is recommended that the steam trap be sized on 3 x the running load at the running differential pressure. This should satisfy the start-up condition and provide proper drainage at minimum loads. When the trap is sized in this way, it will also cater for the start-up load. Consequently, if the drain line to the trap is sized on the trap size, it will never be undersized. For practical purposes, where the drain line is less than 10 m, it can be the same pipe size as the steam trap selected for the application. Drain lines less than 10 m long can also be checked against Appendix 14.3.1 and a pipe size should be selected which results in a pressure loss at maximum flowrate of not more than 200 Pa per metre length, and a velocity not greater than 1.5 m/s. Table 14.3.2 is an extract from Appendix 14.3.1. On longer drain lines (over 10 m), the pressure loss at maximum flowrate should not be more than 100 Pa/m, and a velocity not greater than 1 m/s.

Table 14.3.2 Flow of water in heavy steel pipes

FlowrateCapacity kg/h
Pipe size Ø15
mm
20
mm
25
mm
32
mm
40
mm
50
mm
65
mm
80
mm
100
mm
Pa/mmbar/m<0.15 m/ s0.15 m/s0.3 m/s
900.9173403745162724884716961214940302401.0 m/s
92.50.92517640775616522524478897561515630672
950.9517641476716782560486099001537231104
97.50.975180421778169925964932100441555231500
1001184425788172426325004101521576831932
1201.2202472871189728985508111961735235100
1401.4220511943205931435976121321879238160
1601.62345471015221033736408129962016040680
1801.825258310802354358968041382421420432001.5 m/s
20022666191141248837807200145802264445720
2202.22816521202261739967560153362376047880
2402.42886801256274041767920160562487650400
2602.63067131310285543568244167402592052200
2802.83177421364297045368568173882692854360
30033317671415307846808892180002790056160

Example 14.3.1 An item of plant, using steam at constant pressure, condenses 470 kg of steam an hour at full-load. The pipework between the plant item and the steam trap has an equivalent length of 2 m. Determine the size of pipe to be used. Revised load allowing for start-up = 470 kg /h x 2 = 940 kg /h. As the pipe length is less than 10 metres, the maximum allowable pressure drop is 200 Pa/m. Using Table 14.3.1, by looking across from 200 Pa/m it can be seen that a 25 mm pipe has a capacity of 1 141 kg /h, and would therefore be suitable for the expected starting load of 940 kg /h. Checking further up the 25 mm column, it can be seen that a flowrate of 940 kg /h will incur an actual pressure drop of just less than 140 Pa/m flowing through a 25 mm pipe.

Sizing discharge lines from traps

Sizing discharge lines from traps

The section of pipeline downstream of the trap will carry both condensate and flash steam at the same pressure and temperature. This is referred to as two-phase flow, and the mixture of liquid and vapour will have the characteristics of both steam and water in proportion to how much of each is present. Consider the following example. Example 14.3.2 An item of plant uses steam at a constant 4 bar g pressure. A mechanical steam trap is fitted, and condensate at saturation temperature is discharged into a condensate main working at 0.5 bar g. Determine the proportions by mass, and by volume, of water and steam in the condensate main. Part 1 - Determine the proportions by mass From steam tables:

Learn about steam

Clearly, if 7.9% is flashing to steam, the remaining 100 – 7.9 = 92.1% of the initial mass flow will remain as water. Part 2 - Determine the proportions by volume Based on an initial mass of 1 kg of condensate discharged at 4 bar g saturation temperature, the mass of flash steam is 0.079 kg and the mass of condensate is 0.921 kg (established from Part 1). Water: The density of saturated water at 0.5 bar g is 950 kg/m3,

Learn about steam

From this, it follows that the two-phase fluid in the trap discharge line will have much more in common with steam than water, and it is sensible to size on reasonable steam velocities rather than use the relatively small volume of condensate as the basis for calculation. If lines are undersized, the flash steam velocity and backpressure will increase, which can cause waterhammer, reduce the trap capacity, and flood the process.

Steam lines are sized with attention to maximum velocities. Dry saturated steam should travel no faster than 40 m/s. Wet steam should travel somewhat slower (15 to 20 m/s) as it carries moisture which can otherwise have an erosive and damaging effect on fittings and valves. Trap discharge lines can be regarded as steam lines carrying very wet steam, and should be sized on similarly low velocities. Condensate discharge lines from traps are notoriously more difficult to size than steam lines due to the two-phase flow characteristic. In practice, it is impossible (and often unnecessary) to determine the exact condition of the fluid inside the pipe. Although the amount of flash steam produced (see Figure 14.3.2) is related to the pressure difference across the trap, other factors will also have an effect.

Learn about steam

Factors having a bearing on two-phase flow inside a pipe, include:

  • If the condensate on the upstream side of the trap is cooler than the saturation temperature (for example: a thermostatic steam trap is used), the amount of flash steam after the trap is reduced. This can reduce the size of the line required.
  • If the line slopes down from the trap to its termination, the slope will have an effect on the flow of condensate, but to what magnitude, and how can this be quantified?
  • On longer lines, radiation losses from the line may condense some of the flash steam, reducing its volume and velocity, and there may be a case for reducing the line size. But at what point should it be reduced and by how much?
  • If the discharge line lifts up to an overhead return line, there will be times when the lifting line will be full of cool condensate, and times when flash steam from the trap may evaporate some or all of this condensate. Should the rising discharge line be sized on flash steam velocity or the quantity of condensate?
  • Most processes operate some way below their full-load condition for most of their running cycle, which reduces flash steam for most of the time. The question therefore arises: is there a need for the system to be sized on the full-load condition, if the equipment permanently runs at a lower running load?
  • On temperature controlled plant, the pressure differential across the trap will itself change depending on the heat load. This will affect the amount of flash steam produced in the line. Recommendations on trap discharge lines Because of the number of variables, an exact calculation of line size would be complex and probably inaccurate. Experience has shown that if trap discharge lines are sized on flash steam velocities of 15 to 20 m/s, and certain recommendations are adhered to, few problems will arise. Recommendations:
  1. Correctly sized trap discharge lines which slope in the direction of flow and are open-ended or vented at a receiver, will be non-flooded and allow flash steam to pass unhindered above the condensate (Figure 14.3.3). A minimum slope of 1 in 70 (150 mm drop every 10 m) is recommended. A simple visual check will usually confirm if the line is sloping - if no slope is apparent it is not sloping enough!

Learn about steam

  1. If it is unavoidable, non-pumped rising lines (Figure 14.3.4) should be kept as short as possible and fitted with a non-return valve to stop condensate falling back down to the trap. Risers should discharge into the top of overhead return lines. This stops condensate draining back into the riser from the return main after the trap has discharged, to assist the easy passage of flash steam up the riser.

Learn about steam

It is sensible to consider using a slightly larger riser, which will produce a lower flash steam velocity.

This will reduce the risk of waterhammer and noise caused by steam trying to force a path through the liquid condensate in the riser. Important: A rising line should only be used where the process steam pressure is guaranteed to be higher than the condensate backpressure at the trap outlet. If not, the process will waterlog unless a pumping trap or pump-trap combination is used to provide proper drainage against the backpressure. 3. Common return lines should also slope down and be non-flooded (Figure 14.3.4). To avoid flash steam occurring in long return lines, hot condensate from trap discharge lines should drain into vented receivers (or flash vessels where appropriate), from where it can be pumped on to its final destination, via a flooded line at a lower temperature. Condensate pumping is dealt with in more detail in Module 14.4.

The condensate pipe siz​ing chart

The condensate pipe siz​ing chart

The condensate pipe sizing chart (Figure 14.3.5) can be used to size any type of condensate line, including:

  • Drain lines containing no flash steam.
  • Lines consisting of two-phase flow, such as trap discharge lines, which are selected according to the pressures either side of the trap. The chart (Figure 14.3.5):
  • Works around acceptable flash steam velocities of 15 - 20 m/s, according to the pipe size and the proportion of flash steam formed.
  • Can be used with condensate temperatures lower than the steam saturation temperature, as will be the case when using thermostatic steam traps.
  • Is used to size trap discharge lines on full-load conditions. It is not necessary to consider any oversizing factors for start-up load or the removal of non-condensable gases.
  • May also be used to estimate sizes for pumped lines containing condensate below 100°C. This will be discussed in Module 14.4.

Learn about steam

Using the condensate pipe sizing chart (Also available in Appendix 14.3.2) Establish the point where the steam and condensate pressures meet (lower part of the chart, Figure 14.3.5). From this point, move vertically up to the upper chart to meet the required condensate rate. If the discharge line is falling (non-flooded) and the selection is on or between lines, choose the lower line size. If the discharge line is rising, and therefore likely to be flooded, choose the upper line size. Note: The reasoning employed for the sizing of a steam trap is different to that used for a discharge line, and it is perfectly normal for a trap discharge line to be sized different to the trap it is serving. However, when the trap is correctly sized, the usual ancillary equipment associated with a steam trap station, such as isolation valves, strainer, trap testing chamber, and check valve, can be the same size as the trapping device selected, whatever the discharge line size.

Example 14.3.3 1 On the chart (Figure 14.3.6)

Example 14.3.3 1 On the chart (Figure 14.3.6)

A steam trap passing a full-load of 1000 kg/h at 6 bar g saturated steam pressure through a falling discharge line down to a flash vessel at 1.7 bar g. As the discharge line is non-flooded, the lower figure of 25 mm is selected from the chart (Figure 14.3.5).

Learn about steam

Example 14.3.4 2 on the chart (Figure 14.3.7)

Example 14.3.4 2 on the chart (Figure 14.3.7)

A steam trap passing a full-load of 1 000 kg/h at 18 bar g saturated steam pressure through a discharge line rising 5 m up to a pressurised condensate return line at 3.5 bar g. Add the 0.5 bar static pressure (5 m head) to the 3.5 bar condensate pressure to give 4 bar g backpressure. As the discharge line is rising and thus flooded, the upper figure of 32 mm is selected from the chart, (Figure 14.3.5).

Learn about steam

Example 14.3.5 3 on the chart (Figure 14.3.8)

Example 14.3.5 3 on the chart (Figure 14.3.8)

A steam trap passing a full-load of 200 kg/h at 2 bar g saturated steam pressure through a sloping discharge line falling down to a vented condensate receiver at atmospheric pressure (0 bar g). As the line is non-flooded, the lower figure of 20 mm is selected from the chart, (Figure 14.3.5).

Learn about steam

Example 14.3.6 4 on the chart (Figure 14.3.9)

Example 14.3.6 4 on the chart (Figure 14.3.9)

A pump-trap passing a full-load of 200 kg/h at 4 bar g saturated steam space pressure through a discharge line rising 5 m up to a non-flooded condensate return line at atmospheric pressure. The 5 m static pressure contributes the total backpressure of 0.5 bar g. As the trap discharge line is rising, the upper figure of 25 mm is selected from the chart, (Figure 14.3.5).

Learn about steam

Example 14.3.7 5 on the chart (Figure 14.3.10)

Example 14.3.7 5 on the chart (Figure 14.3.10)

Consider a condensate load of 200 kg/h to a receiver and pump. In this case, the condensate line is based on the maximum capacity of the pump to achieve the desired delivery head. Calculating pump capacities is covered in Module 14.4 'Pumping Condensate from Vented Receivers', but for this example, it is assumed that the maximum condensate load will be 1 200 kg/h. Because the condensate will have lost its flash steam content to atmosphere via the receiver vent, the pump will only be pumping liquid condensate. In this instance, it is only necessary to use the top part of the chart in Figure 14.3.5. As the line from the pump is rising, the upper figure of 25 mm is chosen. Note: If the pumped line were longer than 100 m, the next larger size must be taken, which for this example would be 32 mm. A useful tip for lines of 100 m or less is to choose a discharge pipe which is the same size as the pump. For further details refer to Module 14.4 'Pumping condensate from vented receivers'.

Learn about steam

Common return lines - falling lines

Common return lines - falling lines

It is sometimes necessary to connect several trap discharge lines from separate processes into a common return line. Problems will not occur if the following considerations are met:

  • The common line is not flooded and slopes in the direction of flow to an open end or a vented receiver, or a flash vessel if the conditions allow.
  • The common line is sized on the cumulative sizes of the branch lines, and the branch lines are sized from Figure 14.3.5. Example 14.3.8 Figure 14.3.11 shows three heat exchangers, each separately controlled and operating at the same time. The condensate loads shown are full loads and occur with 3 bar g in the steam space. The common line slopes down to the flash vessel at 1.5 bar g, situated in the same plant room. Condensate in the flash vessel falls via a float trap down to a vented receiver, from where it is pumped directly to the boiler house. The trap discharge lines are sized on full-load with steam pressure at 3 bar g and condensate pressure of 1.5 bar g, and as each is not flooded, the lower line sizes are picked from the graph. Determine the condensate line sizes for the falling discharge lines and common lines.

Learn about steam

Common return lines - rising lines

Common return lines - rising lines

It is sometimes unavoidable for condensate discharge and common lines to rise at some point between the trap and the point of final termination. When this is the case, each discharge line is sized by moving up to the next size on the chart, as previously discussed in this Module. Example 14.3.9 Figure 14.3.12 shows the same three heat exchangers as in Example 14.3.8. However, in this instance, the common line rises 15 m and terminates in an overhead non-flooded condensate return main, giving the same backpressure of 1.5 bar as in Example 14.3.8. Each of the discharge lines is sized as a rising line. Determine the condensate line sizes for the discharge lines and common lines.

Learn about steam

Example 14.3.10 - Falling common line

Example 14.3.10 - Falling common line

Calculating the common line sizes for the application shown in Fig. 14.3.12 which falls to a final termination point:

Learn about steam

Example 14.3.11 - Rising common line

Example 14.3.11 - Rising common line

Calculating the common line sizes for the application shown in Fig. 14.3.14 which rises to a final termination point: Note that the steam loads are the same as Example 14.3.10, but the discharge lines are one size larger due to the rising common line.

Learn about steam

The procedure shown in Examples 14.3.10 and 14.3.11 can be simplified by using Appendix 14.3.3.

For example, where pipes A and B (20 mm and 50 mm) join, the minimum required pipe diameter is shown as 54 mm. Clearly, the user would fit the next largest size of commercial pipe available, unless the calculated bore is close to a nominal bore size pipe.

Appendix 14.3.1 Flow of water in heavy steel pipes

Flowratekg/h
Pipe size Ø15
mm
20
mm
25
mm
32
mm
40
mm
50
mm
65
mm
80
mm
100
mm
Pa/mmbar/m<0.15 m/s0.15 m/s0.3 m/s
100.1501192234907561 4472 9664 6449 432
12.50.125581332525548531 6343 3485 22010 656
150.15651512776169431 8073 7085 76011 736
17.50.175681623026701 0261 9664 0326 26412 744
200.2761763287201 1052 1134 3206 73213 680
22.50.225791873497701 1772 2544 6087 16414 5800.5 m/s
250.25831983718141 2492 3874 8607 59615 408
27.50.275902093898571 3142 5135 1127 99216 200
300.3942204109001 3792 6325 3648 35216 956
32.50.325972304289401 4402 7475 6168 71217 712
350.351012414469791 4982 8585 8329 07218 432
37.50.3751042484641 0151 5552 9666 0489 39619 116
400.41122594791 0511 6093 0716 2649 72019 764
42.50.4251152664971 0871 6633 1756 48010 04420 412
450.451192775111 1231 7173 2726 66010 36821 024
47.50.4751222845261 1561 7683 3706 87610 65621 636
500.51262925401 1881 8143 4637 05610 94422 212
52.50.5251302995581 2201 8653 5537 23611 23222 788
550.551303065721 2491 9123 6367 41611 52023 364
57.50.5751333175831 2821 9583 7447 59611 80823 904
600.61373245981 3102 0023 8167 77612 06024 444
62.50.6251403316121 3392 0483 8887 92012 31224 984
650.651443386261 3682 0923 9968 10012 60025 488
67.50.6751483466371 3972 1314 0688 28012 85225 992
700.71513536521 4222 1744 1408 42413 06826 496
72.50.7251513566621 4512 2184 2128 56813 32027 000
750.751553646771 4762 2574 2848 74813 57227 468
77.50.7751583716881 5052 2974 3568 89213 78827 972
800.81623786981 5302 3364 4649 03614 04028 4401 m/s
82.50.8251663857091 5552 3724 5369 18014 25628 872
850.851663897241 5802 4124 6089 32414 47229 340
87.50.8751693967341 6062 4484 6809 46814 72429 772
900.91734037451 6272 4884 7169 61214 94030 240
92.50.9251764077561 6522 5244 7889 75615 15630 672
950.951764147671 6782 5604 8609 90015 37231 104
97.50.9751804217781 6992 5964 93210 04415 55231 500
10011844257881 7242 6325 00410 15215 76831 932
1201.22024728711 8972 8985 50811 19617 35235 100
1401.42205119432 0593 1435 97612 13218 79238 160
1601.62345471 0152 2103 3736 40812 99620 16040 680
1801.82525831 0802 3543 5896 80413 82421 42043 2001.5 m/s
20022666191 1412 4883 7807 20014 58022 64445 720
2202.22816521 2022 6173 9967 56015 33623 76047 880
2402.42886801 2562 7404 1767 92016 05624 87650 400
2602.63067131 3102 8554 3568 24416 74025 92052 200
2802.83177421 3642 9704 5368 56817 38826 92854 360
30033317671 4153 0784 6808 89218 00027 90056 160

Learn about steam

Appendix 14.3.3 Common pipe sizing table D1 = Connecting branch size (N.B.) D2 = Common pipe size

D2D1 - Connecting branch size (NB)
1520253240506580100
152125293543526781101
162226303643526782101
172326303643536782101
182327313744536782102
192428313744536882102
202528323845546882102
212629333845546883102
222730333946556983102
232730343946556983103
242831354047556984103
252932354147567084103
263033364148567084103
273134374248577084104
283234384349577185104
293335384349587185104
303436394450587285104
313437404551597286105
323538414551597286105
333639414652607387105
343739424752607387106
353840434753617487106
363941444854627488106
374042454954627588107
384143455055637589107
394244465056637689107
404345475157647689108
414446485257657790108
424547495358657790108
434647505459667891109
444648515459677891109
454749515560677992110
464850525661688092110
474951535762698093110
485052545862698193111
495153555963708194111
505254565964718294112
515355576065718395112
525456586166728395113
535557596266738496113
545658606367748597114
555759606468748597114
565859616469758698115
575960626570768698115
D2D1 - Connecting branch size (NB)
1520253240506580100
586061636670778799116
596162646771778899116
6062636568727888100117
6163646669737989101117
6264656770748090101118
6365666871758091102118
6466676972758191102119
6567687072768292103119
6668697173778393104120
6769707274788493104120
6870717275798494105121
6971727376808595106121
7072737477818696106122
7173747578818796107123
7274757679828897108123
7375767780838898108124
7476777881848998109124
7576787982859099110125
76777980828691100110126
77788081838792101111126
78798182848893102112127
79808183858993102112127
80818284868994103113128
81828385879095104114129
82838486889196105115129
83848587899297105115130
84858688909398106116131
85868789919499107117131
86878890929599108117132
878889919396100109118133
888990919497101109119133
899091929598102110120134
909192939698103111120135
919293949699104112121135
9293949597100105113122136
9394959698101106113123137
9495969799102106114123137
95969798100103107115124138
96979899101104108116125139
979899100102105109117126139
9899100101103106110118127140
99100101102104107111118127141
100101102103105108112119128141